COAL MINING - Our Business

PRODUCTION AND PRODUCTIVITY

 A Mini Ratna Company - South Eastern Coalfields Limited has made a record in the year 2009-10    in Production and set an all time highest record in Overall Performance in respect of off-take/despatches, production, wagon loading, quality improvements and optimization of overall  consumers’ satisfaction in terms of meeting their coal requirement.Total Production in the year 2009-10 was 108.01  Million Tonnes against the target of 106  Million Tonnes which is 6.78 % more   than in the year 2008-09.

SECL has also set a historical all time high record of despatch by despatching 105.87 Million Tonnes to its various Consumers during the year 2009-10.  This is an all time high record by any subsidiary of Coal India Limited .

 

                                           DAILY PERFORMANCE REPORTS[CLICK HERE]

 

 

 

                                                 PRODUCTION AND PRODUCTIVITY FROM 1998 - 2010

 

  

 

Production
(mill. Tonnes)

Productivity (Output/manshift)

year OC UG Total OC UG Overall
98-99 41.56 16.00 57.56 9.24 0.92 2.64
99-00 42.75 16.01 58.70 9.36 0.93 2.70
00-01 44.57 15.76 60.33 9.96 0.93 2.83
01-02 48.21 15.91 64.12 10.03 0.97 3.0
02-03 50.44 16.16 66.60 10.70 1.01 3.21
03-04 54.65 16.36 71.01 11.25 1.05 3.49
04-05 61.97 16.58 78.55 12.27 1.11 3.95
05-06 66.50 16.52 83.02 12.76 1.12 4.17
06-07 72.30 16.20 88.50 13.27 1.14 4.51
07-08 77.05 16.74 93.79 14.30 1.19 4.83
08-09 83.58 17.57 101.15 15.76 1.26 5.26
09-10 90.18 17.83 108.01 18.89 1.33 5.96


PERFORMANCE [2009-10]

ITEM ACTUAL % Growth
TOTAL PRODN M.T. 108.01 6.78
O/C PRODN M.T. 90.18 7.90
U/G PRODN M.T. 17.83 1.48
OBR MM3 129.80 21.30
OVERALL OMS Te 5.96 13.31
OC  OMS Te 18.89 19.86
U/G OMS Te 1.33 5.56
COAL OFFTAKE MT 105.89 2.79
WAGON LOADING FWW/DAY 4472 -4.79
SUPPLY TO STEEL PLANT M T 1.50 -0.66

 

DESPATCHES & OFFTAKE [ 2009-10 ]

 

 SECTOR WISE DESPATCH(MT)   (TOTAL DESPATCHES - 105.87 MT) [ 2009-10 ]

Power House CPP UNIT Cement Steel (Blendable)  Sponge Fetilizer Other
74.26 11.25 4.73 0.15 4.39 0.64 10.45

 

 

MODE WISE DESPATCH (MT)  (TOTAL DESPATCHES  - 105.87 MT) [ 2009-10 ]

RAIL ROAD  MGR BELT OTHER /(OWN WAGONS)
40.54 40.43 16.39 5.37 3.14

 

GRADEWISE PRODUCTION [ 2008-09 ]   

GRADE %
A 2.58
B 9.75
C 9.47
D 4.39
E + F 73.67
SC-II 0.14

 

STATE WISE PRODUCTION  (MT)   [ 2008-09 ]

Chhattisgarh             Madhya Pradesh
88.72 (87.71 %) 12.43 (12.29 %)

 

Coal Despatch by Road

 

 

 

line.gif (2998 bytes)